Whole cabinet installation and inspection methods

The overall kitchen cabinet has triggered a new wave of kitchen and bathroom, becoming a new hot spot in modern homes, and the demand of consumers is rising. The whole kitchen cabinet consists of four parts, the cabinet body panel, the door panel, the countertop and the hardware.

1. Quartz stone countertop: First look at the color is not the color selected at the beginning, the second use a hard weapon to test the effect on the countertop; another point is whether the countertop interface is thin, the middle line that is not connected is very thick, the more The finer the better.

2. After installing the cabinet and the cabinet, shake it vigorously to see if it is loose, and whether the installation is secure. The floor cabinet should be shaken before the countertop is installed. There is a level on the construction and installation site. After the cabinet is installed, you can measure it with the level gauge. Whether the row of cabinets is level or not, do not install the slope. The quartz stone countertop is 15mm thick. If the plate is free, it is best to place a 16mm moisture-proof plate (or large core plate) under the countertop.

3. After the table top is installed, the back water will be coated with white glass glue. You have to look at whether the white (mold proof) glass glue is of good quality. Poor glass glue doesn't look very slippery. Good glass glue looks as slippery as jelly. This is a metaphor.

4. The bottom of the basin should have waterproof aluminum mooring. After the basin cabinet is installed, it should be covered with transparent glass glue to strengthen the waterproof inside the basin cabinet. Remember to be sure to use transparent glass glue. If the white glass glue sees water for a long time, the enzyme will be sent badly. The countertop is also the same, so use a good white glass glue.

5. The basin said last time that it should be filled with water to test whether it leaks water. The most important thing is to take over the water pipe. (You should also pay attention to the residual impurities after the dishes or other things are used. The larger ones are washed away in the basin, and the large residual impurities will remain in the lower basin without water. This is often a problem in use, because the downpipe is so large that it will leave impurities for a long time. Send enzymes and block the water.

6. Door panel You should carefully look at the front and back of each piece, whether there are scratches or inconsistent colors.

7. The door hinge should have the best of 6 screw holes. When you install it, you can look it up. After installing it, you can also grab the door and shake it. If the screw is not tightened, the door will be loose or the time will be long. Down, you can learn how to adjust the door hinges at the scene with the masters. It will be useful for you in the future. It will be normal for the door to loosen after a few years. So you just have to learn how to install the door panel and adjust the hinges. It's also very simple. I learned it in a few minutes. Just a screwdriver can do it.

8. After all the doors are installed, you can see if all the door installations are flush, do not install the bumps, it is difficult to see. Is the handle installed loose? 9. The upper and lower, front and rear, left and right slits of the door panel and the drawer surface should be uniform. The middle gap is about 3mm> 3mm is too big to see.

10. Judging whether a set of cabinets is qualified or not depends mainly on two aspects, namely edge edge sealing and seams. The edges include: the edge of the cabinet, the edge of the door panel, and the edge of the countertop; the seam includes: cabinet seams, door seams, joints between the countertop and the cabinet, seams between the countertop and the wall, and seams between the countertop and the cooktop, the sink, etc. .

11. The installation of the range hood should be kept horizontal, firmly fixed on the wall or the connecting plate, and should not be loose or shaken; the distance between the bottom of the hood and the table top is 700mm, too high will affect the smoking effect.

12. Safety is very important. Therefore, all drawers and baskets should be freely pulled, without blockage, and all the exposed sharp corners of the cabinet must be blunt, and the metal parts should be sanded at the touchable position, and no burrs or sharp angles are allowed.

13. The hanging cabinet and the bottom cabinet should be relatively horizontal, and the board should be free of edges and corners. Open the door of the cabinet and put your head in it to smell if there is any smell. Poor plates taste very heavy.

14. The formal installation site should pay attention to civilized construction. Before the construction, clean up the site and remove debris; during construction, pay attention to protecting the product and the site, clean up the garbage in time, do not allow sawdust and smoke to fly, and do not open the customer's range hood to extract smoke; Clean the sawdust and dust in the cabinet, then clean the exterior surface and countertop of the cabinet, and finally clean the site, collect the packaging and the garbage left after construction, and take it away.

15. Finally, the electrical appliance is plugged into the power supply test to see if it works normally. Then, if there is scratch on the surface, is it a prototype? The model is not the style you choose. Others have no major problems. The most important thing is that all electrical appliances cannot be installed. There is looseness (also need to install the level), especially the hood, the looseness will fall, the consequences are serious, the disinfection cabinet installation is loose, and the screws on both sides of the sterilizer are locked. There are 4 screws and 30-35mm long screws. The burner can be loosened, because it should be put into and out, the furnace hole can not be opened too much (actual opening 655 * 355, can be plus or minus 10-15mm), too loose for future operation is not convenient.

16. The door panel of the burner cabinet should have venting holes. It is better to use 4 explosion screws for each hoist than to install 2 hoists. Â